HokieSat ACTION ITEMS
|
Ref |
Action |
Actionee |
Status |
Comments |
|
5/23/02 |
Get
HokieSat model into IDEAS |
Belcher |
CLOSED |
|
|
5/23/02 |
Determine
connector and component pin outs of Panel 2 |
Einsmann |
CLOSED |
Done as much as can with info that we have. Need 1 WB info and info from USU |
|
5/23/02 |
Test
solar cells outside and inside using lamp |
Pressl,
Skelton |
CLOSED |
Testing completed on 5/31. Need to send Swenson and Tyler an email. |
|
5/23/02 |
Sort
fasteners |
Lennox |
CLOSED |
Have 6 boxes now. Assembly team working on getting them into the clean room. |
|
5/23/02 |
Clean
the clean room so it can be used |
Hibbert |
CLOSED |
Cleaned, going to clean once a week. |
|
5/23/02 |
Clean
side panels and place in clean room |
Assembly
Team |
CLOSED |
In clean room on 6/10 |
|
5/30/02 |
Get
people roof certified |
Lennox,
Skelton, Ginde, Kumar, H. Kim |
CLOSED |
Respirators are in. |
|
6/6/02 |
Check
IO board connector with connector on the board to make sure they fit.
Dawgstar had a problem with this |
Jones,
Ginde, Kumar |
CLOSED |
Need to order new one if we can not find it. |
|
6/6/02 |
Test
solar cells for power output |
Gilliom,
Pressl, Skelton |
CLOSED |
Completed. Results in power directory on website |
|
6/6/02 |
GPS
wire lengths to wiring team |
Lennox |
CLOSED |
Completed |
|
6/13/02 |
Determine
connector and component pin outs of Panel 3 and 4 |
Einsmann |
CLOSED |
Done as much as possible |
|
6/13/02 |
Meeting
on July 4 moved to July 2 |
|
CLOSED |
Meeting is on July 2 at 2:30 pm in Rand 221. |
|
6/20/02 |
Send
USU and Cornell their GPS cables/connectors from the first order. |
Schwartz,
Lennox |
CLOSED |
Sent on 6/27 |
|
6/27/02 |
Send
the downlink patch antenna and the science patch cable lengths to Joel at
USU. |
Schwartz,
Jones |
CLOSED |
Sent 7/29/02. |
|
7/9/02 |
Did
we send the IO board and the backplane traveler to USU with the boards?? |
Kumar,
Lennox |
CLOSED |
Package arrived at USU on 7/11 and backplane traveler sent on 7/11 |
|
7/11/02 |
Need
to get TC and comm wire lengths to the wiring team |
Pressl,
Schwartz |
CLOSED |
|
|
6/20/02 |
Compile
wiring and connector questions for USU and Cornell |
Jones,
Schwartz, Einsmann |
CLOSED |
|
|
6/27/02 |
Order
Bbox epoxy (Stycast 2850 FT with Catalyst #9) and
20 gauge wire |
M.
Kim |
CLOSED |
Epxoy has arrived with CofC. Wire delivered 8/9 |
|
8/8/02 |
Send
Fall semester schedules to Lennox to set up a meeting time. |
EVERYONE |
CLOSED |
Meetings at 2:30 on Friday for the semester. |
|
7/18/02 |
Goddard
people coming to visit us. |
Lennox,
Hall, Schwartz |
CLOSED |
Tuesday August 20. Everyone in the lab to meet them. Hall will send out an email. |
|
5/23/02 |
Urelane battery box |
M.
Kim, Schwartz |
CLOSED |
Completed
8/23/02 |
|
5/23/02 |
Figure
out the 1 WB |
Jones |
CLOSED |
|
|
5/23/02 |
Software |
Berry,
Ginde, VanDyke, H. Kim |
|
Move into sub action items |
|
8/30/02 |
Disassemble
the structure and components |
Assembly
team |
CLOSED |
Get done this week. |
|
5/23/02 |
Determine
GPS antenna mounting and placement |
Ginde,
Lennox |
CLOSED |
Ground plane needs to be 70 square mm. Epoxy has arrived. |
|
7/2/02 |
Can
fasteners be used to attach skins to isogrid? |
Lennox |
CLOSED |
Yes if we can go into stay out zones. Need feed back from GSFC |
|
8/1/02 |
Determine
what needs to be done with ground station antennas |
Lennox,
Pressl, Ginde, Skelton, Kumar |
CLOSED |
Uplink antenna mounted. |
|
8/30/02 |
Set
up a time for Orbital wiring class |
Hall,
Lennox, Wiring Team, M. Kim |
CLOSED |
September 17 or 19. Waiting for Hall to determine. |
|
|
Design
and fab new torque coil mounts |
|
CLOSED |
Out of shop. Needs to be iridited. Waiting for other Al parts. |
|
|
Order
new GPS crosslink cables |
Schwartz,
|
CLOSED |
Ordered. Should come arrive in Oct. |
|
|
Order
epoxy (Dow Corning 93-500 silicon) to fix solar cell cover glass |
|
CLOSED |
Have procedure. Needs to be done. Pressl and Winiski will help. Do this on 9/23 |
|
|
Fix
tapped structural hole in side panel |
|
CLOSED |
|
|
|
Clean
side panels |
|
CLOSED |
|
|
|
Onboard
time keeping |
Berry,
Paul |
CLOSED |
USU is taking care of this. |
|
|
Finish
CEE base plate |
Homb |
CLOSED |
Done,
need to iridite |
|
|
Clean
fasteners |
Assembly
team |
CLOSED |
One box left to clean. |
|
|
Design and fab new GPS bracket |
Lennox,
Homb |
CLOSED |
Done,
need to iridite. |
|
|
Determine
materials and components for bake out, schedule time with Goddard |
|
CLOSED |
Can take materials to Orbital. Going to bake out the pigmat soon and the boards later. |
|
|
Test
ground station radios |
Ginde,
Kumar |
CLOSED |
This is on hold for the moment. |
|
|
Pigmat Bakeout |
Skelton |
CLOSED |
Going up over Thanskgiving
break. |
|
|
Need
to get 200°C wire from USU for battery box. |
|
CLOSED |
Got some from A. E. Petsche |
|
|
Move
clean room. |
EVERYONE |
CLOSED |
Done |
|
|
Send
your spring schedules to |
EVERYONE |
CLOSED |
Email me at slennox@vt.edu |
|
|
Power
team needs to have a meeting |
Gilliom,
Schenck, Lee, Kim, Cardoza |
CLOSED |
Tentative time is set for |
|
|
How,
when to install helicoils |
Pedraza,
|
CLOSED |
Pedraza
and |
|
|
Compile
a new fastener order |
|
CLOSED |
Sent into to GSFC |
|
|
Repair
solar cell cover glass |
|
CLOSED |
|
|
|
Fit
check APL boxes with brackets |
|
CLOSED |
|
|
|
Fix
rate gyro board with Tom Mattick’s solution |
VanDyke,
Lee |
CLOSED |
Gyro board is tested and works. |
|
|
Hole
in honeycomb for monopole fasteners |
Homb,
Pedraza |
CLOSED |
Drawing
is in Shop |
|
|
GPS
patch antenna ground plane |
Homb,
|
CLOSED |
Work order is in the shop. |
|
|
Get
loop antenna mounts into shop |
|
CLOSED |
In shop. |
|
|
Make
a list of things good, things that need to be done and big problems for the
software team |
Software
team |
CLOSED |
|
|
|
Ask
Steve if he can fix the power supply in the tracking lab. |
Einsmann |
CLOSED |
Steve says he cleaned it and it is working. |
|
|
Testing
of Magnetometer |
Pressl,
VanDyke |
CLOSED |
Complete |
|
|
Do
we have all needed parts to make flight TC and power boards??? |
Pressl,
Gilliom, Schenck |
CLOSED |
Parts are in. |
|
|
Progress
of items in shop |
|
CLOSED |
|
|
|
Who
is going to be here this summer and what will they be working on? |
Everyone |
CLOSED |
Send an email to |
|
|
Define
thermal nodes and material properties for components |
Belcher,
Langone, |
Open |
Model
is done. Need some kind of MLI to cover zenith and nadir panels. Belcher
needs to send his documentation to Lennox. |
|
5/23/02 |
Prototype
battery pack |
M.
Kim, Lee |
Open |
Need
to complete charge tests of different pack configurations to get max temps
that the batteries will see. Need to call Ken and Michelle about the battery
test plans. Emailed Michelle with questions on programming in Labview. |
|
5/23/02 |
Get
flight loop antenna from Christian (450MHz ± 500kHz) |
|
Open |
Has
a prototype working using the big mounts. Will be handing prototype over to |
|
|
Integration
of computer boards |
Einsmann |
Open |
Loaded a program and trying to run it. CPU board does not work. CPU board layout has been sent to Gilliom. Gilliom thinks that it might be the power conditioning chip. Aroh has pointed out the power pins. We need to figure out what went wrong. |
|
5/23/02 |
Determine
CEE cage modifications for wires and connectors |
Jones |
Open |
Depends on if we are going to get the science board from Utah. |
|
5/23/02 |
Determine
procedure for thermal cycling on boards |
Skelton,
Belcher, Pedraza, Hibbert |
Open |
Got a vacuum. Need to put 50 connectors in the face plate. Need to find some time in the shop to make the face plate. |
|
5/23/02 |
Prototype
and fab power boards |
Gilliom,
Lee, Cardoza |
Open |
Test procedures need to be written and sent to Skelton. Need a formal request to VPT. Need VPT part numbers. Can the power board charge the batteries? We might need a 20V 2 Amp op amp to get the circuit working. |
|
5/23/02 |
Testing
relay board |
Gilliom |
Open |
In the process of testing. Waiting for maxim parts. Need to send out to Tom when the tests are complete. Lennox has solution to connector issue. |
|
5/23/02 |
Design
and fab pcb for 1 WB, and TCs |
Gilliom,
Lee, Cardoza |
Open |
Need to make a prototype. Gilliom has a few more questions for Jones. |
|
5/23/02 |
Prototype
and fab torque coil board |
Schenck,
Lee |
Open |
Testing is complete. Layout has been updated. Test plans complete. Need to order new flight PCB. |
|
|
Determine
what testing can be done and should be done |
Skelton |
Open |
Waiting for test plans. Structural test with Dr. Wicks?? Resend email. |
|
|
Fab
GSE top hat for assembly team |
Pedraza,
Homb, Hibbert |
Open |
Main part done. Extender needs to be made. |
|
|
Update
of the assembly procedure |
Hibbert |
Open |
On hold. |
|
|
Determine
a product that can be used for a thermal path from different board components
to the CEE cage |
Belcher,
|
Open |
We could use the COTHERM that we are looking at with the bbox. |
|
7/11/02 |
Power
budget and sim. |
Aoyagi |
Open |
The power draw needs to stay below 19.2 W. Trying to get it into tasks. |
|
8/1/02 |
Find
the FPGA from Chad |
Gilliom |
Open |
Lennox is trying to figure out what to do on this. Gilliom needs to send me the information on the FPGA that was supposed to be supplied. |
|
8/15/02 |
Write
test plans |
Gilliom,
Schenck, Lee |
Open |
Lee has sent Eugene the TC test plan. Gilliom is working on the one for the power board. |
|
8/22/02 |
Need
2nd tower for downlink? |
|
Open |
Hall’s has the list of things needed for the tower. |
|
8/30/02 |
Update
of Mass SS |
Pressl |
Open |
Updated 030321. Need to update the connectors and fasteners. |
|
8/30/02 |
Update
drawing package |
|
Open |
A few more need to be done. Zullo is working on Bbox drawings. |
|
|
Attitude
determination software |
VanDyke |
Open |
Updating Kalman Filter with a new Rate Gyros idea. Debugging and writing into a task at the moment. |
|
9/6/02 |
Orbit
and attitude control |
|
Open |
Need to look through them. Need to switch to mean elements, include more maneuvers and add power. Need to work on Task manager and timing. Have it working with the orbital class |
|
9/6/02 |
Overall
software arch |
|
Open |
We need to get our messaging program running. Turner is working on his simulator. Needs to test AD software. Have a global spacecraft class. |
|
9/6/02 |
PCM
matrix |
|
Open |
We have a new one. Need to get together and discus. Need
someone that understands comm and its software. |
|
|
The
effect of the nadir pointing angle on comm. |
Lagone, Turner, Hall |
Open |
We need to just get a DL antenna with a big field of view. |
|
|
Make
a trip to EPR for iridite |
|
Open |
Sometime in this next week. |
|
|
Order
new PCBs for Power boards, TC board, 1 WB, TC. |
Gilliom,
Schenck |
Open |
Split into two orders. One for the PCBs and one for the
boards. Wait until battery test on power board is complete. |
|
|
Wiring
Team |
|
Open |
Have a few more pinouts to
figure out with the I/O and power boards. Grounding scheme looks to be good. |
|
|
Determine
placement of four fasteners in side panels |
Pedraza,
Homb |
Open |
Have this started. Need to finish. |
|
|
Determine
how to apply accelerometers to nadir and zenith panels |
Pedraza,
|
Open |
Cornell is looking into what accelerometer to use. |
|
|
Buy cotherm for the battery boxes |
|
Open |
On hold until after the thermal test on the battery box. |
|
|
Fix
GPS bracket 2 |
|
Open |
|
|
|
Crosslink
cables |
|
Open |
All cables have been assigned. The cables have been sent. Waiting
for them to come back. |
|
|
Fix
uplink antenna on roof |
|
Open |
Waiting until classes are over |
|
|
Get
a few new people certified |
|
Open |
Have Van Dyke and Turner get certified to work on the
roof. |
|
|
Formation
Flying software |
|
Open |
|